Regulation 11
of Sewerage and Drainage (Protection of Public Sewerage System) Regulations 2017
Regulation 11
Construction survey following completion of specified activity
Subregulation 1
Upon the completion of any specified activity in a part of a public sewer corridor, the contractor of the activity must —
carry out or cause to be carried out a construction survey to establish whether the public sewerage system which runs through that part of the public sewer corridor is damaged or adversely affected by the activity; and
submit a copy of the report of the construction survey to the Board within the time specified in paragraph (2).
Subregulation 2
For the purposes of paragraph (1), the time is —
such time as may be specified by the Board; or
where the Board does not specify any time —
in the case of a specified activity with a plan requiring the Commissioner’s approval and in respect of which an application is made for the issue of a compliance certificate under section 33(8) of the Act, when the application is made; and (ii)in any other case, when the declaration and certificate of completion of works is submitted under regulation 9(4)(f).
Subregulation 3
A contractor who contravenes paragraph (1) shall be guilty of an offence.