Regulation 15

of Sewerage and Drainage (Protection of Public Sewerage System) Regulations 2017

Regulation 15

Applications to Board

Subregulation 1

An application made to the Board under these Regulations must be in such form and manner as the Board may specify.

Subregulation 2

The Board must consider every application received by it, and may do any of the following:

(a)

grant the application, with or without conditions (including conditions subsequent);

(b)

direct the contractor to comply with such requirements as the Board may specify with respect to the subject matter of the application and resubmit the application within such period as may be specified in the direction;

(c)

refuse to grant the application.

Subregulation 3

Where the application mentioned in paragraph (2)(a) is an application to extend a commencement window period, the Board must, in granting the application, also fix the period of the extension.