Singapore legislation
Regulation 7
of Sewerage and Drainage (Protection of Public Sewerage System) Regulations 2017
Regulation 7
Cessation of approval for plan
Subregulation 1
A plan for any specified activity ceases to be an approved plan —
if the activity does not start before the end of the commencement window period for that activity;
upon the failure of the contractor to comply with any condition or requirement imposed by the Board under regulation 5(3), 12(1)(a) or 15(2)(a) in relation to the approved plan;
in accordance with regulation 10; or
upon the revocation by the Board of the approval for the plan.
Subregulation 2
For the purpose of paragraph (1)(d), the Board may revoke the approval for any plan upon being satisfied of any of the following:
any information or document submitted to the Board in connection with any of the following is false or misleading:
the application for approval of the plan under regulation 5;
any application for permission to amend the plan under regulation 6;
any application for an extension of the commencement window period for the activity under regulation 8;
any measure imposed by the Board under regulation 12(1)(b) has not been complied with.
Subregulation 3
The Board must, before revoking the approval for any plan, give the contractor concerned notice in writing of the Board’s intention to do so specifying a date, not less than 7 days after the date of the notice, on which such revocation is to be made and calling on the contractor to show cause to the Board why the approval should not be revoked.