10. Application of this Part

Feedback & support
Amended

Last amended by an amending law of 2014.

This Part shall apply only to the following types of work that form part of any building operation or works of engineering construction (referred to in these Regulations as high-risk construction work):

(a)

demolition work;

(b)

excavation and trenching work in a tunnel or hole in the ground exceeding 1.5 metres depth;

(c)

lifting operations involving tower, mobile or crawler crane;

(d)

piling work; and (e)tunnelling work. (f)[Deleted by S 278/2014 wef 01/05/2014]

(g)

[Deleted by S 224/2013 wef 01/05/2013]