66. Dismantling
Feedback & supportIt shall be the duty of the occupier of a worksite where any formwork structure situated therein is to be dismantled to comply with paragraphs (2), (3) and (4).
Dismantling of a formwork structure in a worksite shall not commence until the concrete is set.
Materials dismantled from the formwork structure shall be removed promptly or stock-piled in areas where persons are not required to work or pass.
Protruding nails, wire ties and other form of accessories not necessary to subsequent work shall be pulled, cut or otherwise made safe.
Subregulation 1
It shall be the duty of the occupier of a worksite where any formwork structure situated therein is to be dismantled to comply with paragraphs (2), (3) and (4).
Subregulation 2
Dismantling of a formwork structure in a worksite shall not commence until the concrete is set.
Subregulation 3
Materials dismantled from the formwork structure shall be removed promptly or stock-piled in areas where persons are not required to work or pass.
Subregulation 4
Protruding nails, wire ties and other form of accessories not necessary to subsequent work shall be pulled, cut or otherwise made safe.