Skip to content
In forceAmendedUpdated to 1 Jul 2026
Contents

Part 2 · Temporary Relief for Inability to Perform Contracts

7. Additional relief for inability to perform event contract or tourism-related contract

Amended

Last amended by an amending law of 2020.

(1)

This section applies to a case mentioned in section 5 where the scheduled contract is an event contract or a tourism‑related contract and (to avoid doubt) does not limit the operation of that section.

(2)

Despite any law or anything in the contract, another party to the contract may not, after being served with the notification for relief in accordance with section 9(1), at any time (whether during or after the prescribed period) forfeit any deposit (or part of any deposit) taken under the contract on the basis of the subject inability, unless the notification for relief is withdrawn or an assessor has made a determination that the forfeiture of the deposit or any part of the deposit is just and equitable in the circumstances of the case.

(3)

Despite any law or anything in the contract, if the other party to the contract has already forfeited any deposit (or part of any deposit) taken under the contract on the basis of the subject inability, including at any time between 1 February 2020 and the date of commencement of this Part, the other party must on receipt of the notification for relief served in accordance with section 9(1), as soon as practicable restore the deposit or part of the deposit as if it had not been forfeited.

(4)

Despite any law or anything in the contract, the fact that the subject inability was to a material extent caused by a COVID-19 event is a defence to a claim for the payment of a cancellation fee under the contract in respect of the subject inability.

(4A)

Subsection (4) does not apply if —

(a)

the notification for relief is withdrawn; or

(b)

on an application under section 9(2), an assessor makes a determination that the case in question is not one to which section 5 applies, or that the payment of the cancellation fee or any part of it is just and equitable in the circumstances of the case.

(5)

To avoid doubt, subsections (3) and (4) do not affect any judgment, arbitral award, compromise or settlement given or made before the service of the notification for relief.

Report

Part 2A

Rental Relief and Related Measures

Part 3

Temporary Relief for Financially Distressed Individuals, Firms and Other Businesses

Part 4

Temporary Measures for Conduct of Meetings

Part 5

Temporary Measures for Court Proceedings and Syariah Court Proceedings

Part 6

Temporary Measures Concerning Remission of Property Tax

Part 7

COVID‑19 Control Orders

Part 8

Contracts Affected by Delay in the Performance or Breach of a Construction Contract, Supply Contract or Related Contract

Part 8A

Extension of Time for Construction Contracts

Part 8B

Temporary Measures for Cost-Sharing in Construction Contracts

Part 8C

Part 9

Temporary Measures for Conduct of Collective Sale of Property

Part 10

Further Reliefs for Specified Contracts

Part 10A

Part 11

Part 12

Rental Waiver Due to COVID-19 Event in 2021

Schedules