Part 2 · Temporary Relief for Inability to Perform Contracts

4. Application

Amended

Last amended by an amending law of 2020.

(1)

This Part does not apply to —

(a)

a lease or licence of non-residential immovable property entered into or renewed (other than automatically or in exercise of a right of renewal in the lease or licence) on or after 25 March 2020; or

(b)

any other scheduled contract entered into or renewed (other than automatically) on or after 25 March 2020.

(2)

A reference to a scheduled contract in this Act includes one to which the Government is a party.

Report

Part 2A

Rental Relief and Related Measures

Part 3

Temporary Relief for Financially Distressed Individuals, Firms and Other Businesses

Part 4

Temporary Measures for Conduct of Meetings

Part 5

Temporary Measures for Court Proceedings and Syariah Court Proceedings

Part 6

Temporary Measures Concerning Remission of Property Tax

Part 7

COVID‑19 Control Orders

Part 8

Contracts Affected by Delay in the Performance or Breach of a Construction Contract, Supply Contract or Related Contract

Part 8A

Extension of Time for Construction Contracts

Part 8B

Temporary Measures for Cost-Sharing in Construction Contracts

Part 8C

Part 9

Temporary Measures for Conduct of Collective Sale of Property

Part 10

Further Reliefs for Specified Contracts

Part 10A

Part 11

Part 12

Rental Waiver Due to COVID-19 Event in 2021

Schedules