Part 8A · Extension of Time for Construction Contracts

39A. Application and interpretation of this Part

Amended

Last amended by an amending law of 2020.

(1)

This Part applies to a construction contract (including one to which the Government is a party) —

(a)

that was entered into before 25 March 2020, but not if the construction contract was renewed (other than automatically) on or after that date;

(b)

that remains in force on 2 November 2020; and

(c)

where, as at 7 April 2020, any construction works to be performed under the construction contract have not been certified in accordance with the construction contract as completed.

(2)

In this Part —

“completion date”, in relation to any construction works to be performed under a construction contract, means the date by which the construction works must be certified in accordance with the construction contract as completed, failing which liquidated damages become payable by the party failing to so complete the construction works;

“construction works”, in relation to a construction contract, means the construction works (within the meaning given by section 3(1) of the Building and Construction Industry Security of Payment Act (Cap. 30B)) to be performed under the construction contract.

Report

Part 8B

Temporary Measures for Cost-Sharing in Construction Contracts

Part 8C

Part 9

Temporary Measures for Conduct of Collective Sale of Property

Part 10

Further Reliefs for Specified Contracts

Part 10A

Part 11

Part 12

Rental Waiver Due to COVID-19 Event in 2021

Schedules