22FA. Interpretation of this Part
Feedback & supportLast amended by an amending law of 2024. 2 amendments in all.
In this Part —“approved reduction”, in relation to the energy use intensity of a building, means a reduction in the energy use intensity of the building by a percentage approved by the Commissioner of Building Control under section 22FO(3) for that building;“as-built score”, in relation to an existing building which has undergone a major energy use change, means the ES score awarded to that building upon the completion of the major energy use change;“audit report” means a report of the result of an energy audit mentioned in section 22FN(1)(d);“design score”, in relation to an existing building for which a major energy use change is proposed, means the ES score projected for that building upon the completion of the major energy use change, assessed based on the design of the proposed major energy use change;“energy auditor” means a person registered as an energy auditor under section 22FC;“energy efficiency improvement plan” means an energy efficiency improvement plan prepared under section 22FN(1)(c), and includes any energy efficiency improvement plan amended in accordance with section 22FO(4) or 22FS(1);“energy use intensity”, in relation to a building, means the annual energy consumption of the building per unit of gross floor area (expressed in kilowatt hour (kWh) per square metre per year), calculated using the prescribed methodology;“energy use intensity threshold” means the threshold level of energy use intensity prescribed for the purposes of this Part;“energy-intensive building” means a Type 1 building that has an energy use intensity that exceeds the energy use intensity threshold;“environmental sustainability score” or “ES score” means a numerical score to assess the environmental sustainability of a building, calculated using the prescribed scoring methodology;“existing building” means any building in respect of which a certificate of statutory completion or a temporary occupation permit is issued;[Deleted by Act 28 of 2024 wef 30/09/2025]“gross floor area”, in relation to a building, means the aggregate of the gross areas of all floor spaces of the building that are prescribed (whether the floor space is within or outside the building, enclosed, covered or otherwise), but excludes any prescribed excluded area;“major energy use change”, in relation to an existing building, means —
building
“building” means any permanent or temporary building or structure and includes —(a)a hut, shed or roofed enclosure;(b)an earth retaining or stabilising structure, whether permanent or temporary;(c)a dock, wharf or jetty;(ca)a floating structure, not being a boat or vessel, constructed or to be constructed on a flotation system that —(i)is or is to be supported by water;(ii)is not intended for or useable in navigation; and(iii)is or is to be permanently moored;(d)a culvert, crossing, bridge, underpass or tunnel;(da)a fixed installation;(e)a sewage treatment plant, sewer, drain, swimming pool or any non‑proprietary type of concrete tank for the storage of any solid, liquid or gaseous product;(f)a shelter provided under the Civil Defence Shelter Act 1997; and(g)such other erection or structure (whether permanent or temporary) as the Minister may, by order in the Gazette, declare to be a building;
the installation, substantial alteration or replacement of a prescribed cooling system of the building; or
prescribed
“prescribed” means prescribed in the regulations made under section 29L.
any other change to the energy requirements of the building that may be prescribed;“mandatory energy improvement audit notice” or “MEI audit notice” means a mandatory energy improvement audit notice issued under section 22FJ(1);“mechanical engineer” means a professional engineer registered under the Professional Engineers Act 1991 in the branch of mechanical engineering who has in force a practising certificate issued under that Act;“minimum environmental sustainability standard”, in relation to any building, means the prescribed minimum standard of environmental sustainability applicable to that building, or to a building of that type or class, expressed in terms of a ES score and other specified requirements;[Deleted by Act 28 of 2024 wef 30/09/2025]“specified reduction”, in relation to the energy use intensity of a building, means a reduction in the energy use intensity of the building by a prescribed percentage;“Type 1 building” means an existing building, or part of an existing building, of any class or type for the time being prescribed for the purposes of Divisions 2, 3 and 4;“Type 2 building” means an existing building, or part of an existing building, of any class or type for the time being prescribed for the purposes of Division 5.
registered
“registered” or “registration” means registered or registration under this Part authorising the person registered to carry on any registrable activity or a class of registrable activity specified in the registration;
“approved reduction”, in relation to the energy use intensity of a building, means a reduction in the energy use intensity of the building by a percentage approved by the Commissioner of Building Control under section 22FO(3) for that building;
Commissioner of Building Control
“Commissioner of Building Control”, in relation to this Act or any Part or provision of this Act, means any Commissioner of Building Control appointed under section 3(1) to be responsible for the operation of this Act or that Part or provision, as the case may be;
“as-built score”, in relation to an existing building which has undergone a major energy use change, means the ES score awarded to that building upon the completion of the major energy use change;
“audit report” means a report of the result of an energy audit mentioned in section 22FN(1)(d);
“design score”, in relation to an existing building for which a major energy use change is proposed, means the ES score projected for that building upon the completion of the major energy use change, assessed based on the design of the proposed major energy use change;
“energy auditor” means a person registered as an energy auditor under section 22FC;
“energy efficiency improvement plan” means an energy efficiency improvement plan prepared under section 22FN(1)(c), and includes any energy efficiency improvement plan amended in accordance with section 22FO(4) or 22FS(1);
“energy use intensity”, in relation to a building, means the annual energy consumption of the building per unit of gross floor area (expressed in kilowatt hour (kWh) per square metre per year), calculated using the prescribed methodology;
floor area
“floor area” means the total area of floor space within the building measured between party walls including the thickness of external walls;
“energy use intensity threshold” means the threshold level of energy use intensity prescribed for the purposes of this Part;
“energy-intensive building” means a Type 1 building that has an energy use intensity that exceeds the energy use intensity threshold;
“environmental sustainability score” or “ES score” means a numerical score to assess the environmental sustainability of a building, calculated using the prescribed scoring methodology;
“existing building” means any building in respect of which a certificate of statutory completion or a temporary occupation permit is issued;
certificate of statutory completion
“certificate of statutory completion” means a certificate of statutory completion issued under section 12;
“gross floor area”, in relation to a building, means the aggregate of the gross areas of all floor spaces of the building that are prescribed (whether the floor space is within or outside the building, enclosed, covered or otherwise), but excludes any prescribed excluded area;
“major energy use change”, in relation to an existing building, means —
the installation, substantial alteration or replacement of a prescribed cooling system of the building; or
any other change to the energy requirements of the building that may be prescribed;
“mandatory energy improvement audit notice” or “MEI audit notice” means a mandatory energy improvement audit notice issued under section 22FJ(1);
“mechanical engineer” means a professional engineer registered under the Professional Engineers Act 1991 in the branch of mechanical engineering who has in force a practising certificate issued under that Act;
“minimum environmental sustainability standard”, in relation to any building, means the prescribed minimum standard of environmental sustainability applicable to that building, or to a building of that type or class, expressed in terms of a ES score and other specified requirements;
“specified reduction”, in relation to the energy use intensity of a building, means a reduction in the energy use intensity of the building by a prescribed percentage;
“Type 1 building” means an existing building, or part of an existing building, of any class or type for the time being prescribed for the purposes of Divisions 2, 3 and 4;
“Type 2 building” means an existing building, or part of an existing building, of any class or type for the time being prescribed for the purposes of Division 5.