In force2001 Revised EditionCurrent version · 2001 Revised EditionSee versions on Singapore Statutes Online(opens the publisher’s site)
11. Disposal of silt
Feedback & supportThe licensee of a sand quarry shall ensure that —
(a)
each silting pond is provided with an overflow weir which shall be of permanent construction and set at half a metre below the top of the bund of such pond;
(b)
all the silt from any sand washing operation shall flow into the silting ponds referred to in regulation 3 and is not carried into any existing stream, canal or drain; and
(c)
when each silting pond is full, another silting pond shall be used and arrangements made for the removal of the silt from the full silting pond to a suitable place approved by the Licensing Officer.