Regulation 11

Review of airport licensee’s draft master plan or proposals

Subregulation 1

Upon receipt from an airport licensee of any draft master plan submitted under rule 4, 5(1) or 6(1), or any proposal for amendments submitted under rule 7(1), the Authority must, within a period of 4 months after receiving the draft master plan or proposal, as the case may be, review the draft master plan or proposal with a view to ––

(a)

approving the draft master plan or the proposal; or

(b)

refusing to approve the draft master plan or the proposal,and to that end, may do anything it considers necessary or convenient for the purposes of the review, but subject to these Rules.

Subregulation 2

Subject to these Rules, the Authority may conduct any such review in the manner it considers appropriate and, in particular, may —

(a)

consult with any person;

(b)

receive submissions from those persons it considers appropriate;

(c)

hold seminars or workshops; or

(d)

conduct hearings.

Subregulation 3

In conducting any such review, the Authority is not bound by rules of evidence but may inform itself of any matter in any manner it considers appropriate.