Regulation 19

of Building Control Regulations 2003

Regulation 19

Validity period of approval or deemed approval

Amended byS 54/2008 wef 15/02/2008S 854/2023 wef 18/12/2023

For the purposes of section 5B(1)(c) of the Act, the approval or deemed approval of any plans of building works granted by the Commissioner of Building Control shall lapse if the building works are not commenced within 24 months from the date of approval or deemed approval, as the case may be.