Regulation 21

of Building Control Regulations 2003

Regulation 21

Permit to carry out structural works

Amended byS 54/2008 wef 15/02/2008S 54/2008 wef 15/02/2008S 54/2008 wef 15/02/2008

Subregulation 1

Amended byS 54/2008 wef 15/02/2008

An application for a permit to carry out any structural works (including piling or site formation works or the demolition of a building) under section 6(1) of the Act shall be in such form as the Commissioner of Building Control may require.

Subregulation 2

Where any part of a building under construction or undergoing alteration is to be demolished, no separate permit for the demolition works shall be required.

Subregulation 3

Amended byS 54/2008 wef 15/02/2008

For the purposes of section 6(2)(e) of the Act, an application for a permit to carry out any demolition of a building shall be accompanied by —

(a)

a method statement detailing how the demolition works are to be carried out; and

(b)

an impact assessment report on surrounding buildings.

Subregulation 4

Amended byS 54/2008 wef 15/02/2008

For the purposes of section 6(2)(e) of the Act, an application for a permit to carry out any piling or site formation works shall be accompanied by —

(a)

an impact assessment report on surrounding buildings and other structures; and

(b)

a notification specifying the date of commencement of the piling or site formation works.