Requirements for deviation from approved plans

Amended byS 54/2008 wef 15/02/2008S 54/2008 wef 15/02/2008S 665/2013 wef 01/04/2014S 54/2008 wef 15/02/2008S 665/2013 wef 01/04/2014S 665/2013 wef 01/04/2014S 54/2008 wef 15/02/2008S 665/2013 wef 01/04/2014S 443/2017 wef 10/09/2017S 854/2023 wef 18/12/2023

Subregulation 1

Amended byS 54/2008 wef 15/02/2008

Where it is desired that any building works deviate from the approved plans of those building works, an application shall be made to the Commissioner of Building Control under section 5A(1) of the Act and shall, without prejudice to that section, be accompanied by the amended plan of the buildings works showing clearly the departures or deviations.

Subregulation 2

Amended byS 54/2008 wef 15/02/2008

Where the deviations involve material changes to the structural design, the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act and, in the case of major building works, the accredited checker shall submit the structural plans and design calculations to the Commissioner of Building Control for approval before construction.

Subregulation 2A

Amended byS 665/2013 wef 01/04/2014

Where the deviations involve material changes to building works other than the structural design, the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act shall submit the building plans to the Commissioner of Building Control for approval before construction.

Subregulation 3

Amended byS 54/2008 wef 15/02/2008S 665/2013 wef 01/04/2014

Notwithstanding paragraph (1), where the departures or deviations involve immaterial changes to the structural design, the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) shall only be required to prepare and submit to the Commissioner of Building Control —

(a)

the record plans;

(b)

his certificate stating that to the best of his knowledge and belief the departures or deviations do not affect the structural adequacy or stability of the building;

(c)

a certificate from an accredited checker stating that to the best of his knowledge and belief, the record plans do not show any inadequacy in key structural elements of the building to be erected or affected by building works carried out in accordance with those plans; and

(d)

on the completion of the building works, a report stating the departures and deviations accompanied by the detailed structural plans and design calculations showing such departures and deviations.

Subregulation 3A

Amended byS 665/2013 wef 01/04/2014

Notwithstanding paragraph (1), where the departures or deviations involve immaterial changes to building works other than the structural design, the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act shall only be required to prepare and submit to the Commissioner of Building Control —

(a)

the record plans;

(b)

his certificate stating that to the best of his knowledge and belief, the departures or deviations —

(i)

have been completed in accordance with the provisions of the Act and these Regulations; and

(ii)

do not affect the objectives and performance requirements set out in the Fifth Schedule relating to the approved plans; and

(c)

such other certificate or document as may be required by the Commissioner of Building Control.

Subregulation 4

Amended byS 54/2008 wef 15/02/2008

The qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act shall keep and maintain a record of all departures and deviations relating to the structural elements of the building works.

Subregulation 5

Amended byS 665/2013 wef 01/04/2014

The certificates referred to in paragraphs (3)(b) and (c) and (3A)(b) and (c) shall be in such form as the Commissioner of Building Control may specify.

Subregulation 6

Amended byS 443/2017 wef 10/09/2017S 854/2023 wef 18/12/2023

Every application under section 5A(1) of the Act must be accompanied by the appropriate fee specified in the Second Schedule.