Regulation 23
Regulation 23
Submission of progress reports and certificates
Subregulation 1
For the purposes of section 9(4)(e) of the Act, the supervising qualified person appointed in respect of any building works shall prepare and submit the following reports and certificates relating to the building works at the corresponding times or intervals of the building works, where applicable:
[Deleted by S 54/2008 wef 15/02/2008](b)[Deleted by S 54/2008 wef 15/02/2008](c)a notice of completion of all piling works carried out, a record plan showing full details of the piling works and a certificate of supervision of those piling works within 28 days of completion of those piling works; (d)on completion of all building works, his certificate stating that the building works have been carried out under his supervision; and
within 14 days of his ceasing to carry out his duties under the Act, a summary report of all those building works which have been carried out under his supervision and a certificate of such supervision.
Subregulation 2
The certificates referred to in paragraph (1)(c), (d) and (e) shall be in such form as the Commissioner of Building Control may require.