Approval and deemed approval of plans

Amended byS 54/2008 wef 15/02/2008S 54/2008 wef 15/02/2008S 854/2023 wef 18/12/2023S 854/2023 wef 18/12/2023

Subregulation 1

Amended byS 54/2008 wef 15/02/2008

Where the Commissioner of Building Control approves any plans of building works under section 5(3)(a) of the Act, he shall notify the developer of the building works and the qualified person who prepared and submitted those plans of his approval and of the terms and conditions, if any, subject to which the approval has been granted.

Subregulation 2

Amended byS 54/2008 wef 15/02/2008S 854/2023 wef 18/12/2023S 854/2023 wef 18/12/2023

For the avoidance of doubt, no approval of any plans of building works under section 5(3)(a) of the Act, or deemed approval of any plans of lodgment works under section 5AA(1) of the Act, shall be taken to —

(a)

confer any title to land; (b)act as a waiver of any term in any lease or licence; (c)grant any exemption from or permit any contravention of any provision of these Regulations; or (d)waive or modify the application of these Regulations to those building works where no such waiver or modification has been granted under section 6A(1) of the Act in relation to the building works.